Upward trend in imported solar PV module prices to impact the viability of recently awarded solar PV energy projects: ICRA
The imported photovoltaic (PV) module prices have shown an
upward trend over the last three to four-month period, increasing by about 15%,
from about 30-32 cents /watt in May 2017 to about 35-37 cents/watt in August
2017. This increase is due to factors such as a) advancement of module sourcing
from China by companies in the USA, in anticipation of imposition of
anti-dumping duty on Chinese modules by December 2017, and b) extension of
feed-in tariff regime for solar power projects in China till September 2017
(source: industry), thereby increasing demand. In ICRA’s view, such pricing
pressure on imported PV modules, if sustained over the next three to six-month
period, will have an adverse impact on the viability of the recently bid solar
power projects, where the bid tariff is below Rs. 3.5/unit. However, the
magnitude of the impact will vary based on the tariff level and other assumptions.
Further, any delays in delivery schedule and/or dishonoring of price terms
agreed earlier by Chinese OEMs for supplies to the Indian IPPs having solar
power projects under implementation, may lead to the risk of delays along with
cost over-run. Given the present circumstances, where attempts are being made
for renegotiation / cancellation of power purchase agreements (PPA)s by
distribution utilities in a few states, any project execution / completion
delay by the developers beyond the scheduled completion date as per PPA is a
critical risk factor.
The solar PV energy project capacity awarded (both through
the National Solar Mission and the State Policy route) with a bid tariff below
Rs. 3.5/kwh as on August 2017 stood at 3250 MW, within which 750 MW bid
capacity has a tariff below Rs. 3/unit (varying between Rs. 2.44/unit and
2.65/unit) and the balance 2500 MW capacity is with a bid tariff of above Rs.
3/unit (varying between Rs. 3.15/unit and 3.47/unit). As per ICRA estimates, a
6 cent/watt increase in the PV module price is estimated to result in an
increase of about 11% in the capital cost, which in turn is estimated to result
in a decline in cumulative average debt service coverage ratio (DSCR) by 0.12
times and decline in project IRR by 180 basis points for a solar power project
with tariff of Rs. 2.5 per unit, assuming a debt: equity ratio of 70:30,
INR-USD exchange rate of 65, cost of debt at 9.5% post commissioning with a
debt repayment tenure of 18 years and a PLF level of 24% (with DC-AC ratio of
1.3 times and degradation factor of 0.5% per year). In this context, viability
of solar bid tariffs remain critically dependent upon the capital cost, PLF
level and availability of a long tenure debt at cost competitive rate. With
imported PV module content, the capital cost for solar PV energy project
remains exposed to volatility in both i.e. PV module price level and INR-USD
exchange rate.
As seen from Chart 1, the competitively bid-based solar
power bid tariff has been on a declining trend over the past five years with
tariff declining from more than Rs. 12 per unit to less than Rs. 3 per unit.
The tariff of Rs. 2.44 per unit discovered in the bidding for Badla solar park
in Rajasthan in May 2017 is the lowest tariff in the solar power sector. The
significant decline in solar power bid tariff as seen in the last six to
eight-month period was supported by a decline in PV module prices, softening in
the interest rate cycle and also the expectations by project bidders/IPPs
towards further softening in PV module price level over the next six to nine
months. However, the recent upward trend in the PV module prices due to reasons
mentioned earlier, if sustained, would have an adverse impact on the viability
of the recently bid solar power projects, where bid tariff is below Rs.
3.5/kwh.
The following table illustrates the sensitivity of capital
cost for a solar power project to module prices and exchange rate. As the
module price increases from 0.30 US$/watt to 0.38 US$/watt at a exchange rate of
65 INR/USD, the capital cost is estimated to increase from Rs. 4.34 crore per
MW to Rs. 5.01 crore per MW. This in turn would adversely affect the viability
of competitively bid based solar power projects having fixed bid tariff over
the PPA period. At a tariff rate of Rs. 2.5 per unit, the increase in module
prices from 0.30 US$/watt to 0.38 US$/watt would lead to a decline in
cumulative DSCR from 1.20 times to 1.05 times, at an exchange rate at 65
INR/USD.
The following table illustrates the sensitivity of project
IRR for a competitively bid-based solar power project with tariff of Rs. 2.5
per unit to module prices and exchange rate. As the module price increases from
0.30 US$/watt to 0.38 US$/watt at an exchange rate of 65 INR/USD, the project IRR
is estimated to decline from 8.5% to 6.2%.
In addition to the module prices, the cumulative DSCR for a
solar power project also remains highly sensitive to the interest rates. As
seen here, the cumulative DSCR decreases from 1.11 times to 1.01 times as the
interest rate is increased from 9.00% to 11.00% at a module price of 0.36
US$/watt and exchange rate of 65 INR/USD..
For Latest News on Renewable Energy, Climate and Electric Vehicle Visit
www.climatesamurai.com
Comments
Post a Comment